Dean Drive Extension

Document

The Dean Drive Extended Project  (T-030) extends Dean Drive approximately 1,500 feet from the existing cul-de-sac, south of Nokesville Road, to the Animal Shelter driveway. 

  • The extended roadway section will have curbs, gutters, and sidewalks on both sides. Existing culverts will be extended and stormwater management will be included, and Foster Drive will be modified to include two T-intersections and realigned with Dean Drive.

Project Status:

  • On site survey and investigatory fieldwork: October 2018 – March 2019
  • Design to be completed: Winter 2019/2020
  • Begin construction: Spring 2020

City Staff:

Lance Kilby, City Engineer: 703-257-8251

get notified Stay up-to-date on what happening by subscribing below